Offshore Wind Rebate Program/Order Granting Extension of Time to Garden State Offshore Energy (GSOE) (Docket #EO08110971)

Source/Sponsor: 
New Jersey Board of Public Utilities (BPU)
Creator/Author: 
New Jersey Board of Public Utilities (BPU)
Description: 

The New Jersey Board of Public Utilities (BPU) rules that installation of buoy system was delayed for reasons not within Garden State Offshore Energy's (GSOE's) control, and so a third extension was warranted from May 31, 2011 to July 31, 2011.

pdf
Publication Date: 
Wednesday, June 15, 2011
1 MB
Resource Type: 
Document