New England Electricity Scenario Analysis

Source/Sponsor: 
Independent System Operator-New England (ISO-NE)
Creator/Author: 
Independent System Operator-New England (ISO-NE)
Description: 

The study examined the reliability, economic, and environmental impacts of seven different future scenarios for meeting New England's electricity needs in the 2020-2025 timeframe. Scenario #6 included approximately 20 million MWh from existing and new onshore and offshore wind facilities, and assumed the need for additional electricial transmission facilities at a cost of $581 million to $3.9 billion.

pdf
Publication Date: 
Thursday, August 2, 2007
955 KB
Resource Type: 
Document